Moore Street Bridge

Demolition and reconstruction of existing bridge deck at Moore Street Leichhardt.

  • Demolition of existing bridge deck around live services
  • Reconstruction of existing bridge while maintaining traffic flows
  • Remedial works to existing sandstone abutments and stormwater pipes
  • Combination of precast deck units and post-tensioned slab
  • Pavements, guardrails and road furniture

Forestville Pedestrian Bridge

Supply and installation of steel arch pedestrian bridge over Warringah Road at Forestville.

  • Supply and installation of steel arch bridge
  • Construction of concrete abutments and lift shafts
  • Adjustment of existing roads, footpaths and utilities
  • Adjustment of existing traffic signals
  • Installation of lifts and services for new bridge

North Parramatta Pedestrian Bridge

Supply and installation of steel arch pedestrian bridge over Pennant Hills Road at North Parramatta.

  • Supply and installation of steel arch bridge
  • Construction of piled foundations, stairs and lift shafts
  • Hard and soft landscaping
  • Relocation of utilities, street lighting, traffic signals and CCTV
  • Removal and reinstatement of heritage sandstone pillars

Haberfield Pedestrian Bridge

Construction of a steel beam pedestrian bridge over Parramatta Road east of Bland Street.

  • Placement of steel box girder beam
  • Concrete access stairways
  • Lift shafts for wheelchair accessible lifts on each abutment
  • Handrails, bridge screens, lighting and pedestrian fencing
  • All works to RTA Specifications

Heathcote Pedestrian Bridge

Construction of pedestrian bridge over the Princes Highway at Heathcote.

  • Concrete access stairways
  • Wheelchair accessible lift shafts
  • Handrails and bridge screens
  • Lighting and pedestrian fencing

White Bay Passenger Terminal Access Road

Upgrade of City West Link intersection and construction of new internal port access road.

  • Upgrade of City West Link and James Craig Rd intersection
  • Construction of 1km of internal road (Port Access Rd)
  • Bridge construction and new stormwater system
  • New gatehouse and Sydney Ports signage
  • Street lighting and security fencing