- Location One Central Park, Chippendale
- Client Frasers Property Pty Ltd
- Contract Value $9.0 million
- Completion August, 2014
Structures
Carlton United Brewery Building Upgrade
Description of Work
Upgrading of the 120 year old heritage listed Carlton United Brewery Building
This scope of works included:-
– Approvals and Constraints
– Sustainability and Green Star Initiatives
– Inspections
– Building 30 – Demolition, excavation and substantial upgrade of the structure to accommodate 6 new cooling towers and an architectural enclosure.
– Building 25 – Demolition of existing and construction of a new fire stair between buildings 22 and 26, with a new structural steel walkway to connect the new cooling tower enclosure to a fire egress.