- Location Anzac Parade, Maroubra
- Client AbiGroup Ltd
- Contract Value $3.1 million
- Completion February, 2004
Excavation & Earthworks
Pacific Square Residential Complex
Description of Work
Christie Civil undertook the major civil contract related to the Pacific Square residential complex. Works included:
– Excavation of 60,000m³, predominantly in sand /li>
– Demolition of ground slabs and mass concrete pad footings
– Diversion of main drainage pipeline 1500mm to 1800mm diameter
– Construction of stormwater pipeline chambers
– Pipe jacking of 1650mm diameter pipes under Anzac Parade